Vernon River Structure Replacement

Service Details & Examples

In June of 2022 ICS was awarded the contract to replace a structure under the confederation trail in Vernon River. The original structure was placed in 1929 and was buried over 15 meters below the elevation of the trail. As a part of the work a new steel culvert was installed and the existing stream realigned. In total over 20,000 cubic meters of soil was removed and replaced while also having to deal with Hurricane Fiona in the midst of the project.

Budget:
$1.6 Million

Date Completed:
November 25, 2022

Foreman:
Brad Murnaghan